The Hanoi Department of Construction recently issued a traffic diversion plan to ensure safety for the construction of projects to renovate, upgrade, and build new drainage infrastructure. These projects target the Resco, Ecohome, Tay Ho Tay, Diplomatic Corps, and Ciputra urban areas, as well as the Vo Chi Cong, Long Bien, Dong Anh, and Gia Lam areas.
On Xuan Tao Road, from the DT4 intersection to Hoang Quoc Viet Road, the construction unit will install a rolling barrier, 20 m long and 3 m wide, for underground culvert installation. The remaining road width will be an average of 12 m. Specifically, the section leading to Nguyen Van Huyen overpass will be 9 m for traffic. This work will be carried out from 16/2 to 31/3.
On the right service road of Thang Long Avenue, from Km9+750 to Km10+000 in the direction of Hoa Lac, a mobile rolling barrier, 20 m long and 4 m wide, will be set up, leaving 7 m of road width. Construction will take place from 22h to 5h the following day, from 16/2 to 31/3.
On Lai Yen Road in the Bac An Khanh urban area, half of the road will be barricaded to connect culverts to a temporary pump station. The lane from Thang Long Avenue into An Khanh urban area will have 5 m for vehicles to pass.
![]() |
Barrier at Hang Da market area for underground anti-flooding reservoir. Photo: Vo Hai. |
Previously, from 14/2 to 31/5, the city implemented traffic diversions at the Hang Da market area to construct an underground regulating tank and renovate the drainage pipe along Phung Hung Street. Cars will travel one-way on Duong Thanh Street, from the Duong Thanh - Hang Dieu - Nguyen Van To T-junction to the Duong Thanh - Phu Doan - Hang Bong intersection. Some turns are prohibited in the Hong Ha cinema area.
At the end of 2025, the city launched 10 urgent anti-flooding projects with a total investment of nearly 5.600 billion VND, requiring major items to be largely completed before the 2026 rainy season.
The 10 urgent anti-flooding projects in Hanoi are:
| No. | Project Name | Total Investment (billion VND) | Completion Time |
| 1 | Renovation, upgrading, and new construction of drainage infrastructure to address flooding in Resco, Ecohome, Tay Ho Tay, Diplomatic Corps, Ciputra urban areas, and Vo Chi Cong, Long Bien, Dong Anh, Gia Lam areas | 262 | Q2/2026 |
| 2 | Renovation of Thuy Phuong canal for emergency water replenishment to To Lich River and enhanced localized flood control in Resco, Ecohome, Diplomatic Corps, Tay Ho Tay, Ciputra, and adjacent areas | 869 | Q3/2026 |
| 3 | Renovation of the downstream Kim Nguu route connecting To Lich River to Yen So Pumping Station | 700 | Q3/2026 |
| 4 | Upgrading the capacity of existing pumping stations, combining with the installation of temporary pumping stations, and renovating or constructing new drainage culverts and ditches to address flooding along Thang Long Avenue | 163 | Q2/2026 |
| 5 | Investment in building Phu Do Regulating Lake, Tu Liem ward, Hanoi | 800 | Q4/2026 |
| 6 | Investment in building Yen Nghia 2 Regulating Lake, An Khanh commune, Hanoi | 250 | Q4/2026 |
| 7 | Construction and additional installation of lake pumping stations, regulating tanks, and drainage pipeline systems for the To Lich and Ta Nhue river basins | 590 | Q2/2026 |
| 8 | Investment in building Thuy Phuong 2 Regulating Lake, Dong Ngac ward, Hanoi | 717 | Q4/2026 |
| 9 | Investment in building Yen Nghia 1 Regulating Lake, An Khanh commune, Hanoi | 858 | Q4/2026 |
| 10 | Investment in building Me Tri Headworks Lake (Dong Bong 2 Lake, Dai Mo ward) | 370 | Q4/2026 |
Vo Hai