Hau Giang - Ca Mau expressway opening delayed

Prolonged rain has left several sections unfinished, preventing the more than 73 km Hau Giang - Ca Mau expressway from opening on 31/12 as initially planned.

On the evening of 30/12, the My Thuan Project Management Board, under the Ministry of Construction and the project's investor, announced that the expressway, originally slated for operation at 9 am today, has been delayed due to adverse weather. The route is now expected to open in January 2026.

The expressway through Tri Phai commune, Ca Mau province in mid-late December. *Photo: Chuc Ly*

The Hau Giang – Ca Mau section represents an investment of over 17,150 billion VND. It is part of the larger Can Tho – Ca Mau expressway project, which spans nearly 111 km, features four lanes, and has a total capital exceeding 27,500 billion VND. A related segment, the 37.65 km Can Tho – Hau Giang section, opened on 22/12.

Once fully operational, the entire expressway will significantly cut travel time from TP HCM to Ca Mau, reducing it to approximately 3.5–4 hours. This represents nearly a 50% reduction compared to using National Highway 1.

The completed route helps connect the expressway seamlessly from Ca Mau to TP HCM. *Graphic: Hoang Chuong*

An Binh

By VnExpress: https://vnexpress.net/cao-toc-hau-giang-ca-mau-lui-thoi-gian-thong-xe-5000267.html
Tags: Breaking news opening delayed Ca Mau Hau Giang Expressway

News in the same category

Road connecting Nha Trang - Da Lat after over 100 landslides cleared

Road connecting Nha Trang - Da Lat after over 100 landslides cleared

The Khanh Le Pass on National Highway 27C, connecting Nha Trang and Da Lat, has reopened after being closed for over one month due to landslides, though some damaged sections remain barricaded for repairs.

Medical center costing over 60 billion VND left unfinished

Medical center costing over 60 billion VND left unfinished

Hoang Mai Medical Center, an investment exceeding 60 billion VND, began construction in 2020. Its phase one is now complete but remains non-operational due to design adjustments and funding shortages.

Over 20 central TP HCM roads closed for fireworks display

Over 20 central TP HCM roads closed for fireworks display

Vehicles will be restricted from over 20 central city roads to allow residents to enjoy New Year's Eve fireworks on the night of 31/12, according to an announcement from the Traffic Police Department of TP HCM.

Dharma assembly opens at Mandala Tay Thien stupa

Dharma assembly opens at Mandala Tay Thien stupa

A new year dharma assembly will take place at Mandala Tay Thien stupa in Tam Dao commune, presided over by spiritual master Gyalwa Dokhampa of the Drukpa lineage from 31/12/2025 to 2/1/2026.

Cold air descends on northern Vietnam

Cold air descends on northern Vietnam

A strong cold front will affect northern Vietnam on the first day of 2026, pushing temperatures down, with high-altitude areas seeing temperatures below 7 degrees Celsius.

Prime Minister: striving to complete 'Quang Trung campaign' by mid-january 2026

Prime Minister: striving to complete 'Quang Trung campaign' by mid-january 2026

The Prime Minister called for the mobilization of all forces to participate, striving to complete the entire Quang Trung campaign by 15/1/2026, achieving accomplishments to celebrate the 14th Party Congress.

Why is the dedicated bicycle lane in Ho Chi Minh City painted red?

Why is the dedicated bicycle lane in Ho Chi Minh City painted red?

The red paint on Ho Chi Minh City's first priority bicycle lane aims to increase visibility and ensure safety, as many sections share space with cars and motorbikes.

Can Tho 2 bridge expected to break ground in 2026

Can Tho 2 bridge expected to break ground in 2026

The Can Tho 2 bridge, spanning the Hau river and connecting the Ho Chi Minh City - Ca Mau expressway, has a total investment of nearly 30.000 billion dong and is expected to break ground in 2026, with completion after five years.

Passenger traffic at Tan Son Nhat surges during New Year holiday

Passenger traffic at Tan Son Nhat surges during New Year holiday

This year's four-day New Year holiday is expected to see passenger numbers at Tan Son Nhat rise by nearly 20% compared to the same period, with peaks of 135,000 daily passengers.

Over 2,700 workers laid off before Tet to receive 13th-month salary

Over 2,700 workers laid off before Tet to receive 13th-month salary

Panko Vina garment company in former Binh Duong will pay a 13th-month salary to over 2,700 workers laid off before Tet, as its factory is set to close from early February 2026.

Eng English
China 中国人
  • News
  • World
  • Business
  • Entertainment
  • Sports
  • Law
  • Education
  • Health
  • Lifestyle
  • Travel
  • Science
  • Digital
  • Automobiles
FPT Tower, 10 Pham Van Bach Street, Dich Vong Ward,
Cau Giay District, Hanoi, Vietnam
Email: contacts@vnportal.net
Tel: 028 7300 9999 - Ext 8556
Advertise with us: 090 293 9644
Register
© Copyright 2025 vnnow.net. All rights reserved.
Terms of use Privacy policy Cookies