![]() |
The T1 road, with its overpasses connecting to T2, is largely complete. The 4.28 km route has 6 lanes and is built to urban main road standards, with a speed limit of 80 km/h.Photo: Quynh Tran |
The T1 and T2 road project, launched in July 2023, connects Long Thanh International Airport with National Highway 51 and the Ho Chi Minh City - Long Thanh - Dau Giay Expressway. The project has a total value of over 2,630 billion VND.
While the initial contract set completion for the end of 2025, the investor and contractors expedited the project to open the T1 route in time for the upcoming National Day celebrations.
The image shows the intersection of T1 (horizontal) and T2 roads on 26/7, now connected to Long Thanh International Airport. The entire route features three major intersections: T1 with T2, T2 with the Long Thanh - Dau Giay Expressway, and T3 with National Highway 51.
![]() |
About one km away, the T1 intersection with National Highway 51 is also taking shape, with the main section and connecting roads asphalted.Photo: Quynh Tran |
The T1 road, with its overpasses connecting to T2, is largely complete. The 4.28 km route has 6 lanes and is built to urban main road standards, with a speed limit of 80 km/h.Photo: Quynh Tran
![]() |
Most of the T1 road is now asphalted and awaiting lane markings. The median strip is being landscaped.Photo: Quynh Tran |
About one km away, the T1 intersection with National Highway 51 is also taking shape, with the main section and connecting roads asphalted.Photo: Quynh Tran
![]() |
Approximately 3 km away, the T2 route, designed with 4 lanes and built to expressway standards with a speed limit of 100 km/h, is under construction, focusing on the main road and connections to T1 and the Long Thanh - Dau Giay Expressway.Photo: Phuoc Tuan |
![]() |
The T2 route is over 80% complete, with the cement-concrete reinforcement largely finished. This road, connecting the Ho Chi Minh City - Long Thanh - Dau Giay Expressway to T1, is a key part of Long Thanh International Airport's infrastructure and is expected to be finished by the end of the year.Photo: Phuoc Tuan |
Most of the T1 road is now asphalted and awaiting lane markings. The median strip is being landscaped.Photo: Quynh Tran
![]() |
At the T2 intersection with the Long Thanh - Dau Giay Expressway, the overpass framework is in place, and contractors are preparing to install beams for the bridge over the expressway.Photo: Phuoc Tuan |
Many sections of the T1 road, including lighting, railings, and landscaping, are nearing completion after over two years of work. The project is expected to be completed three months ahead of schedule.
Once operational, the T1 route will allow vehicles to travel from Long Thanh International Airport to the Ben Luc - Long Thanh Expressway, the Bien Hoa - Vung Tau Expressway, provincial roads 25B and 25C, and the Ho Chi Minh City Ring Road 3.
![]() |
At this intersection, workers, vehicles, and machinery are working to expedite progress on the overpasses.Photo: Phuoc Tuan |
Approximately 3 km away, the T2 route, designed with 4 lanes and built to expressway standards with a speed limit of 100 km/h, is under construction, focusing on the main road and connections to T1 and the Long Thanh - Dau Giay Expressway.Photo: Phuoc Tuan
![]() |
Some sections of the T2 road are being asphalted to ensure timely connection with T1 and the expressway.Photo: Phuoc Tuan |
The T2 route is over 80% complete, with the cement-concrete reinforcement largely finished. This road, connecting the Ho Chi Minh City - Long Thanh - Dau Giay Expressway to T1, is a key part of Long Thanh International Airport's infrastructure and is expected to be finished by the end of the year.Photo: Phuoc Tuan
![]() |
Contractors have mobilized nearly 1,000 personnel and over 200 pieces of equipment, working in three shifts across 20 work areas to accelerate the project.Photo: Phuoc Tuan |
At the T2 intersection with the Long Thanh - Dau Giay Expressway, the overpass framework is in place, and contractors are preparing to install beams for the bridge over the expressway.Photo: Phuoc Tuan
![]() |
At this intersection, workers, vehicles, and machinery are working to expedite progress on the overpasses.Photo: Phuoc Tuan
![]() |
Some sections of the T2 road are being asphalted to ensure timely connection with T1 and the expressway.Photo: Phuoc Tuan
![]() |
![]() |
Contractors have mobilized nearly 1,000 personnel and over 200 pieces of equipment, working in three shifts across 20 work areas to accelerate the project.Photo: Phuoc Tuan
![]() |
Meanwhile, construction continues at Long Thanh International Airport on the terminal, runway, air traffic control tower, aircraft parking areas, and fuel supply facilities, aiming for completion of the first phase by the end of the year. In this phase, the airport will handle 25 million passengers and 1.2 million tons of cargo annually.
The 5,000-hectare Long Thanh International Airport project has a projected total investment of approximately 336,630 billion VND. Phase two, scheduled for completion in 2035, will add a passenger terminal and a runway, increasing capacity to 50 million passengers and 1.5 million tons of cargo annually. The final phase, targeted for completion between 2030 and 2040, will enable the airport to handle 100 million passengers and 5 million tons of cargo each year.
![]() |
Route map of T1 and T2 roads connecting Long Thanh International Airport. Graphics: Ta Lu
Upon completion, the T1 and T2 roads will connect Long Thanh International Airport with existing roads to Ho Chi Minh City, Binh Duong, Ba Ria - Vung Tau, and other southern provinces. T1 will also serve as the main route for transporting machinery and equipment for future construction phases of the airport.
Quynh Tran - Phuoc Tuan