Long Thanh airport construction faces shortage of 2,000 workers

The Long Thanh airport construction site currently employs over 7,100 direct workers but still needs 1,500-2,000 more, particularly for the passenger terminal and internal road packages.

This information was detailed by Airports Corporation of Vietnam (ACV) in its 20/7 report on project progress and preparations for trial operation and eventual commissioning of Long Thanh airport.

According to ACV, component project three, which includes essential airport facilities, has reached nearly 78% of its contractual progress, with major construction and installation packages at almost 70%. While the site maintains an average of 7,170 direct workers, an additional 1,500-2,000 personnel are still needed as the project enters its critical final phase.

The labor shortfall is particularly acute in the passenger terminal, internal road packages, and various finishing works. ACV has instructed contractors to boost their workforce, aiming for nearly 9,000 direct workers. They also need to add indirect personnel to expedite construction, equipment installation, acceptance procedures, and documentation.

Workers constructing the roof of Long Thanh Airport Passenger Terminal. Photo: Phuoc Tuan

For the passenger terminal, considered the "heart" of Long Thanh airport, construction is over 77% complete. Contractors are currently engaged in wall construction and plastering, waterproofing, painting, tiling, and installing ceilings, partitions, and interior fittings, as well as landscaping.

This component is expected to be completed in September for trial operations, with the airport aiming to commence full operations from 1/12.

Beyond the labor shortage, the rainy season significantly impacts progress, particularly for outdoor works. ACV noted that the 2025 rainy season caused delays of two to four months for certain tasks.

To mitigate these impacts, the investor has instructed contractors to organize appropriate schedules, prioritize indoor construction during heavy rainfall, and proactively manage materials and personnel. Drainage systems, catch basins, and backup pumps must also be strategically placed in construction zones, with work plans adjusted according to weather conditions.

The electricity and water supply systems, crucial for both construction and airport operations, are nearing completion. ACV is collaborating with Dong Nai Water Supply Joint Stock Company to connect and deliver water to various user units. Earlier, the electrical system from the 110 kV substation was successfully energized at the airport's receiving station.

Overview of Long Thanh airport in 7/2026. Photo: Phuoc Tuan

Long Thanh airport spans approximately 5,000 hectares, with a total investment nearing 16 billion USD. Phase one is designed to handle 25 million passengers and 1.2 million tons of cargo annually. It is expected to commence operations by the end of this year, aiming to alleviate pressure on Tan Son Nhat airport and stimulate regional development.

Under the operational division plan proposed by ACV, Long Thanh will manage all international routes exceeding 1,000 km, non-scheduled international flights, and new routes that Tan Son Nhat cannot accommodate. For domestic services, Vietnamese airlines will have the flexibility to choose to operate from Long Thanh based on their needs.

Phuoc Tuan

By VnExpress: https://vnexpress.net/cong-truong-san-bay-long-thanh-thieu-toi-2-000-lao-dong-5099399.html
Tags: passenger terminal ACV labor shortage Long Thanh airport

News in the same category

Coral 'forests' at Hon Chong beach previously damaged by tourists

Coral 'forests' at Hon Chong beach previously damaged by tourists

Clusters of horn and plate corals, along with sea anemones and crinoids, form a rich ecosystem at Hon Chong beach, where two tourists were recently fined 50 million dong for breaking over 10,5 kg of reef-building organisms.

Two more fallen soldiers' remains found at Da Sap cave

Two more fallen soldiers' remains found at Da Sap cave

On the afternoon of 20/7, authorities discovered two more fallen soldiers' remains in the Da Sap cave area, Ha Nha commune, bringing the total number of remains recovered there to 7 after more than two weeks of searching.

Hanoi to break ground on 114 social housing projects

Hanoi to break ground on 114 social housing projects

The city aims to commence construction on 114 social housing projects in the coming months, simultaneously bringing approximately 46,000 apartments to the market.

Found three fallen soldiers' remains at Cau Nhi

Found three fallen soldiers' remains at Cau Nhi

After more than 10 days of searching in Cau Nhi, Nam Hai Lang commune, recovery forces discovered and exhumed three fallen soldiers' remains along with many artifacts.

Driver dies after hitting construction barrier on Noi Bai - Lao Cai expressway

Driver dies after hitting construction barrier on Noi Bai - Lao Cai expressway

A truck driver from Tuyen Quang died after crashing into a construction barrier on the Noi Bai - Lao Cai expressway on the afternoon of 20/7.

Central Committee discusses views on amending land law

Central Committee discusses views on amending land law

On its first working day, the 3rd plenum of the 14th Central Committee discussed perspectives on amending the land law, aiming to refine policies and enhance the efficiency of land management and use.

Former Bac Giang secretary Bui Van Hai stripped of all party positions

Former Bac Giang secretary Bui Van Hai stripped of all party positions

The Central Committee has stripped Bui Van Hai, former secretary of the Bac Giang Provincial Party Committee, of all his party positions due to violations that caused very serious consequences.

Localities with favorable conditions to merge half of schools

Localities with favorable conditions to merge half of schools

A directive from the Prime Minister mandates localities with favorable conditions to reduce 50% of independently operating public schools through mergers, allowing former facilities to function as satellite campuses to ensure students can continue their education close to home.

Tornado-like vortex spreads embers, igniting protective forest

Tornado-like vortex spreads embers, igniting protective forest

A tornado-like vortex, appearing as the Nghi Yen landfill burned, swept embers 100 m to a nearby protective forest, incinerating 1,3 ha of pine trees in Hai Loc commune, Nghe An.

Proposal for over 10,600 billion VND to expand national highway 1 from Da Nang to Vinh Long

Proposal for over 10,600 billion VND to expand national highway 1 from Da Nang to Vinh Long

The Vietnam Road Administration proposes upgrading twelve bypasses and three interchanges on national highway 1 across eight provinces and cities, covering a total length of 70 km with an investment exceeding 10,600 billion VND.

Eng English
China 中国人
  • News
  • World
  • Business
  • Entertainment
  • Sports
  • Law
  • Education
  • Health
  • Lifestyle
  • Travel
  • Science
  • Digital
  • Automobiles
FPT Tower, 10 Pham Van Bach Street, Dich Vong Ward,
Cau Giay District, Hanoi, Vietnam
Email: contacts@vnportal.net
Tel: 028 7300 9999 - Ext 8556
Advertise with us: 090 293 9644
Register
© Copyright 2026 vnnow.net. All rights reserved.
Terms of use Privacy policy Cookies