Long Thanh airport construction faces shortage of 2,000 workers

The Long Thanh airport construction site currently employs over 7,100 direct workers but still needs 1,500-2,000 more, particularly for the passenger terminal and internal road packages.

This information was detailed by Airports Corporation of Vietnam (ACV) in its 20/7 report on project progress and preparations for trial operation and eventual commissioning of Long Thanh airport.

According to ACV, component project three, which includes essential airport facilities, has reached nearly 78% of its contractual progress, with major construction and installation packages at almost 70%. While the site maintains an average of 7,170 direct workers, an additional 1,500-2,000 personnel are still needed as the project enters its critical final phase.

The labor shortfall is particularly acute in the passenger terminal, internal road packages, and various finishing works. ACV has instructed contractors to boost their workforce, aiming for nearly 9,000 direct workers. They also need to add indirect personnel to expedite construction, equipment installation, acceptance procedures, and documentation.

Workers constructing the roof of Long Thanh Airport Passenger Terminal. Photo: Phuoc Tuan

For the passenger terminal, considered the "heart" of Long Thanh airport, construction is over 77% complete. Contractors are currently engaged in wall construction and plastering, waterproofing, painting, tiling, and installing ceilings, partitions, and interior fittings, as well as landscaping.

This component is expected to be completed in September for trial operations, with the airport aiming to commence full operations from 1/12.

Beyond the labor shortage, the rainy season significantly impacts progress, particularly for outdoor works. ACV noted that the 2025 rainy season caused delays of two to four months for certain tasks.

To mitigate these impacts, the investor has instructed contractors to organize appropriate schedules, prioritize indoor construction during heavy rainfall, and proactively manage materials and personnel. Drainage systems, catch basins, and backup pumps must also be strategically placed in construction zones, with work plans adjusted according to weather conditions.

The electricity and water supply systems, crucial for both construction and airport operations, are nearing completion. ACV is collaborating with Dong Nai Water Supply Joint Stock Company to connect and deliver water to various user units. Earlier, the electrical system from the 110 kV substation was successfully energized at the airport's receiving station.

Overview of Long Thanh airport in 7/2026. Photo: Phuoc Tuan

Long Thanh airport spans approximately 5,000 hectares, with a total investment nearing 16 billion USD. Phase one is designed to handle 25 million passengers and 1.2 million tons of cargo annually. It is expected to commence operations by the end of this year, aiming to alleviate pressure on Tan Son Nhat airport and stimulate regional development.

Under the operational division plan proposed by ACV, Long Thanh will manage all international routes exceeding 1,000 km, non-scheduled international flights, and new routes that Tan Son Nhat cannot accommodate. For domestic services, Vietnamese airlines will have the flexibility to choose to operate from Long Thanh based on their needs.

Phuoc Tuan

By VnExpress: https://vnexpress.net/cong-truong-san-bay-long-thanh-thieu-toi-2-000-lao-dong-5099399.html
Tags: passenger terminal ACV labor shortage Long Thanh airport

News in the same category

Proposed land use map for seven wards along the Red River

Proposed land use map for seven wards along the Red River

According to the proposed plan, the Red River urban subdivision spans over 11,400 hectares, stretching from Hong Ha Bridge to Me So Bridge, encompassing seven wards: Thuong Cat, Dong Ngac, Phu Thuong, Hong Ha, Bo De, Long Bien, and Linh Nam.

Passenger bus crashes into tractor-trailer, one dead

Passenger bus crashes into tractor-trailer, one dead

A 24-seat passenger bus collided with the rear of a tractor-trailer that had a flat tire on the Phap Van - Cau Gie expressway, killing the assistant driver instantly on the morning of 8/9.

How Hanoi plans to transform the Red River into a development axis

How Hanoi plans to transform the Red River into a development axis

Hanoi aims to designate the areas along the Red River as a green corridor, while simultaneously developing transportation, urban, economic, cultural, and service functions.

Car plunges into pit on Bien Hoa - Vung Tau expressway

Car plunges into pit on Bien Hoa - Vung Tau expressway

A 7-seater car collided with a warning sign and plunged into a road under repair, falling into a manhole and sustaining heavy damage, shortly after entering the Bien Hoa - Vung Tau expressway.

Centuries-old structures around Hoan Kiem Lake

Centuries-old structures around Hoan Kiem Lake

Many French-era buildings around Hoan Kiem Lake remain functional today after numerous renovations, including Ba Kieu Temple, Vu Thach Pagoda, Hanoi Post Office, and the Hanoi Moi newspaper office.

Three proposed locations for a new airport in Can Tho

Three proposed locations for a new airport in Can Tho

A consulting firm has proposed studying three potential sites for a new airport in Can Tho: Tran De, the former southern Soc Trang, and an area about 30 km from the existing airport.

New kitchen inaugurated for highland students in Son La

New kitchen inaugurated for highland students in Son La

Hope Foundation and FPT Japan recently inaugurated a new kitchen for Na Loc students, replacing a dilapidated corrugated iron structure that had been in use for 13 years.

Research on preserving mass graves of nearly 600 martyrs in Le Thi Rieng Park

Research on preserving mass graves of nearly 600 martyrs in Le Thi Rieng Park

Ho Chi Minh City will study designating the area where nearly 600 martyrs' remains were discovered in Le Thi Rieng Park for protection, constructing a memorial, and creating a historical relic dossier.

Nguyen Thanh Nhan nominated for Dong Thap chairman

Nguyen Thanh Nhan nominated for Dong Thap chairman

Nguyen Thanh Nhan, 49, deputy secretary of the Party Committee of Central Party Agencies, has been assigned as deputy secretary of the Provincial Party Committee and nominated to be elected chairman of Dong Thap Provincial People's Committee.

Progressive Fees Proposed to Deter Project Land Hoarding

Progressive Fees Proposed to Deter Project Land Hoarding

Project developers who leave land unused or slowly utilized may face increasing fees over time; land not put into use after 60 months will be reclaimed.

Eng English
China 中国人
  • News
  • World
  • Business
  • Entertainment
  • Sports
  • Law
  • Education
  • Health
  • Lifestyle
  • Travel
  • Science
  • Digital
  • Automobiles
FPT Tower, 10 Pham Van Bach Street, Dich Vong Ward,
Cau Giay District, Hanoi, Vietnam
Email: contacts@vnportal.net
Tel: 028 7300 9999 - Ext 8556
Advertise with us: 090 293 9644
Register
© Copyright 2026 vnnow.net. All rights reserved.
Terms of use Privacy policy Cookies