Bien Hoa - Vung Tau expressway not open temporarily before Tet

Safety concerns over incomplete sections and legal hurdles mean the Bien Hoa - Vung Tau expressway is not ready for temporary opening before Tet Nguyen dan.

The inter-agency inspection team concluded this after a field visit to the expressway on the afternoon of 12/2. The team included representatives from Road Management Area IV, Team 6 - Department 6 of the Traffic Police Department, Dong Nai Department of Construction, Project Management Board 85 (Ministry of Construction), Vietnam Expressway Development Investment Corporation, Airports Corporation of Vietnam (ACV), and other related units.

According to the inspection results, although the main route is largely complete, all parties agreed that the Bien Hoa - Vung Tau expressway does not yet meet safety standards and lacks the necessary procedures for a temporary one-way opening from Vung Tau to Bien Hoa. The remaining sections will continue to be completed.

The Bien Hoa - Vung Tau expressway at its intersection with T2 of the Long Thanh airport project. Photo: Phuoc Tuan

The Bien Hoa - Vung Tau expressway at its intersection with T2 of the Long Thanh airport project. Photo: Phuoc Tuan

Specifically, some sections of the guardrails are still under construction, protective fences are not fully enclosed, and the system of road signs and markings is incomplete. Many open connections to branch roads have not been closed, posing potential safety risks if the expressway were put into operation.

ACV representatives stated that the T2 connection section, related to the Long Thanh airport area, has not had its road markings completed. The lighting system there also lacks power connections, as it depends on infrastructure within the airport, with completion anticipated by 4/2026. Consequently, this connection section is not safe for use. ACV also has no plans for acceptance testing or temporary opening before Tet due to traffic safety concerns and incomplete legal procedures.

Contractors also recommended against allowing vehicles to circulate at this time to avoid risks, as the process of completing legal procedures and acceptance testing cannot meet the proposed schedule.

The route of the Bien Hoa - Vung Tau expressway. Graphic: Dang Hieu

The route of the Bien Hoa - Vung Tau expressway. Graphic: Dang Hieu

Concluding the inspection, all parties agreed to record all feedback for Project Management Board 85 to continue completing outstanding items and to swiftly finalize legal procedures as regulated.

The Bien Hoa - Vung Tau expressway is nearly 54 km long, features 4-6 lanes, and has a total investment of approximately 17,800 billion VND. The section passing through Ba Ria - Vung Tau (formerly) is 19,5 km long and was once hoped to open before Tet. When the entire route is operational, travel time from central TP HCM to Vung Tau will shorten from about 120 minutes to 70 minutes.

Previously, Project Management Board 85 proposed opening the main route of the Bien Hoa - Vung Tau expressway, the section from Long Thanh interchange to component project 3, before Tet Nguyen dan and temporarily opening it one-way from Vung Tau to Bien Hoa. However, this proposal was not approved after multiple inspections.

Phuoc Tuan

By VnExpress: https://vnexpress.net/cao-toc-bien-hoa-vung-tau-chua-thong-xe-tam-truoc-tet-5040869.html
Tags: Dong Nai Tet Nguyen dan Bien Hoa - Vung Tau expressway

News in the same category

An Truyen village busy preparing banh chung and banh tet for Tet

An Truyen village busy preparing banh chung and banh tet for Tet

Residents of An Truyen village are busy making banh chung and banh tet for offerings during the Tet Binh Ngo Lunar New Year.

Hanoi gateways congested, Ho Chi Minh City clear on eve of Tet

Hanoi gateways congested, Ho Chi Minh City clear on eve of Tet

Roads at Hanoi's gateways were heavily congested with vehicles heading to hometowns, while Ho Chi Minh City's gateways were clear on the afternoon of 13/2 (26th day of the 12th lunar month).

Party and state leaders pay respects to President Ho Chi Minh and former leaders

Party and state leaders pay respects to President Ho Chi Minh and former leaders

On the morning of 13/2, general secretary To Lam led a delegation of party and state leaders to visit President Ho Chi Minh's mausoleum, offer incense in remembrance of heroic martyrs at the Bac Son monument, and pay respects to former leaders at Mai Dich cemetery.

Multi-vehicle collision in Lam Dong leaves three dead

Multi-vehicle collision in Lam Dong leaves three dead

A severe accident involving a tractor-trailer, a truck, and two motorbikes occurred on National Highway 14 through Nhan Co commune (formerly Dak Nong), resulting in three fatalities on the morning of 13/2.

Beer pub fire in Bac Ninh claims one life

Beer pub fire in Bac Ninh claims one life

A staff member was trapped and died after a beer pub caught fire in Nam Son ward in the early morning of February 13.

Cold air mass sweeps into northern region on new year's eve

Cold air mass sweeps into northern region on new year's eve

A moderate cold front is expected to move into the northern region on the eve of the Lunar New Year, Binh Ngo.

Tan Son Nhat airport packed with overseas Vietnamese returning for Tet

Tan Son Nhat airport packed with overseas Vietnamese returning for Tet

Thousands from various provinces and cities waited overnight until early morning in the lobby and corridors of Tan Son Nhat Airport to welcome relatives returning from abroad for Tet, on the evening of 13/2.

Solutions aim to cut travel time from HCMC city center to Long Thanh airport to 30 minutes

Solutions aim to cut travel time from HCMC city center to Long Thanh airport to 30 minutes

The completion of expressways and ring roads will enhance airport connectivity infrastructure, but experts say a long-term metro system is essential to reduce travel time from Ho Chi Minh City city center to Long Thanh.

Spring flower street along the Huong river

Spring flower street along the Huong river

The park on both banks of the Huong river was adorned with various flowers and mascots to celebrate the Binh Ngo Lunar New Year, prominently featuring a pair of blue and red horses symbolizing harmonious yin and yang.

Inside the park and memorial, once the 'Chu Hoa villa' area

Inside the park and memorial, once the 'Chu Hoa villa' area

The villa complex at 1 Ly Thai To, originally owned by the Chu Hoa family and abandoned for years, has been renovated into a park and memorial, opening on the evening of 12/2 (the 25th day of the 12th lunar month).

Eng English
China 中国人
  • News
  • World
  • Business
  • Entertainment
  • Sports
  • Law
  • Education
  • Health
  • Lifestyle
  • Travel
  • Science
  • Digital
  • Automobiles
FPT Tower, 10 Pham Van Bach Street, Dich Vong Ward,
Cau Giay District, Hanoi, Vietnam
Email: contacts@vnportal.net
Tel: 028 7300 9999 - Ext 8556
Advertise with us: 090 293 9644
Register
© Copyright 2026 vnnow.net. All rights reserved.
Terms of use Privacy policy Cookies