Eng English
China 中国人

Eng English
China 中国人
  • News
  • World
  • Business
  • Entertainment
  • Sports
  • Law
  • Education
  • Health
  • Lifestyle
  • Travel
  • Science
  • Digital
  • Automobiles
  • Trở lại Thể thao
  • News
Monday, 8/12/2025 | 05:02 GMT+7

Major components of Long Thanh airport are taking shape

Key facilities at Long Thanh airport, including runways, the passenger terminal, air traffic control tower, radar station, fuel tanks, and state agency offices, are nearing completion.

The passenger terminal, considered the "heart" of the project, is notably nearing completion. Construction began in 2023 with a total investment of 35,000 billion VND. The structural phase is expected to conclude in 2025, with all components finalized by August 2026.

The terminal package, featuring a lotus petal design, has taken shape following the roof installation. Workers are currently busy with the final stages of the roof construction, aiming to complete the building phase in time for a technical flight on 19/12.

The project comprises a central terminal and three wings, designed with separate departure and arrival routes. The structure includes one ground floor and three upper floors, with a roof peak height exceeding 45 m and a total floor area of approximately 376,000 square meters.

Nearby, the air traffic control tower and its auxiliary facilities, with a total investment of 3,500 billion VND, have largely completed their construction. The tower’s design, resembling a lotus bud, harmonizes in color and architecture with the passenger terminal. Standing 123 m tall with a radar installed at its peak, the tower has a construction area of about 80 square meters and a shaft diameter of 10 m.

At the base of the tower, auxiliary facilities such as the technical building, VIP building, power station, and ATC area landscaping are being urgently implemented.

Inside the air traffic control tower, specialized air traffic management equipment and systems are being installed, ensuring readiness for the upcoming technical flight. Once operational, the facility will serve as the "brain" for all takeoff and landing operations, ensuring the safety of hundreds of thousands of flights annually.

The surveillance radar system has taken form, with the mechanical and electronic components fully installed.

The installed radar complex includes a primary surveillance radar (PSR) and a secondary surveillance radar (SSR), fully meeting the standards of the International Civil Aviation Organization (ICAO) and Eurocontrol. When operational, the radar system will expand surveillance coverage and enhance air traffic management quality.

Runway one at the airport is complete and illuminated at night. The runway, 4 km long and 70 m wide, can accommodate the most advanced aircraft available today.

Adjacent to it, the second runway (left) is gradually taking shape after half a year of construction. This runway is 4 km long and 75 m wide. Having two runways provides redundancy in case one encounters issues, which is essential for a high-capacity airport.

The aircraft fuel supply system, with a total capital of over 2,800 billion VND, commenced construction in October 2024 and is expected to be completed next year. According to the design, the Long Thanh airport fuel station will have a capacity of 5,200 cubic meters per day, comprising six fuel tanks.

Each tank has a capacity of 6,000 cubic meters, along with an underground pipeline system leading to the apron, ensuring large-scale fuel storage and supply capabilities.

The project to construct state agency offices, with a total capital of approximately 765 billion VND, is entering its final completion phase.

These components include the headquarters of the Southern Airports Authority, Customs, Immigration Department, local Police, Animal Quarantine, and Plant Quarantine. The Ministry of Construction announced that the structures have largely completed their building phase and are being finalized, ensuring completion before 19/12.

Long Thanh airport, phase one, spans 1,810 hectares. Construction began on 5/1/2021, with a capacity for 25 million passengers and 1,2 million tons of cargo annually. The project aims for substantial completion before 19/12 and commercial operation by mid-2026.

Overview of Long Thanh airport. Photo: ACV

Location of Long Thanh airport and connecting routes to TP HCM. Graphic: Hoang Thanh

Quynh Tran - Phuoc Tuan

By VnExpress: https://vnexpress.net/nhieu-hang-muc-tai-san-bay-long-thanh-lo-dien-4990438.html
Tags: Dong Nai Long Thanh airport

News in the same category

Truck rear-ends tractor-trailer, two dead

Truck rear-ends tractor-trailer, two dead

A truck collided with the rear of a tractor-trailer on the Bung - Van Ninh expressway on the morning of 8/12, killing two people and injuring three.

Police officer rescues female student from container truck

Police officer rescues female student from container truck

Seeing a container truck speeding downhill with signs of losing control, lance corporal Nguyen Mai Thi ran to pull a female student to safety, narrowly escaping danger.

Tropical depression weakens rapidly

Tropical depression weakens rapidly

Due to interaction with cold air, the tropical depression is forecast to weaken rapidly and is unlikely to impact mainland Vietnam.

Hanoi's air quality returns to very unhealthy levels

Hanoi's air quality returns to very unhealthy levels

After a week of weather-induced improvement, Hanoi's air quality deteriorated to very unhealthy levels on the evening of 7/12, with air quality index (AQI) stations exceeding 200 and fine particulate matter (PM2.5) increasing.

Gia Bac Pass in Lam Dong reopens after nearly 5 days of closure

Gia Bac Pass in Lam Dong reopens after nearly 5 days of closure

Vehicles resumed travel on Gia Bac Pass, National Route 28, connecting Binh Thuan and Lam Dong, from the afternoon of 7/12, following efforts by construction crews to clear earth and rock from 20 landslide locations.

Ho Chi Minh City initiates comprehensive fire safety review after blaze kills 4

Ho Chi Minh City initiates comprehensive fire safety review after blaze kills 4

The City People's Committee has mandated all forces to inspect homes combined with businesses that have modified signs and "tiger cages" obstructing escape routes.

TP HCM breaks ground on social housing project for police force

TP HCM breaks ground on social housing project for police force

The city breaks ground on a social housing project featuring over 420 apartments in Binh Phu ward (formerly District 6), designed to accommodate around 1,000 people.

Northern Vietnam set for strong cold front

Northern Vietnam set for strong cold front

A strong cold front is expected to sweep across northern Vietnam from mid-next week, bringing risks of frost and snow on high mountain peaks.

Two irrigation reservoirs in Binh Thuan increase water discharge

Two irrigation reservoirs in Binh Thuan increase water discharge

Song Quao and Song Luy irrigation reservoirs in Binh Thuan have increased water discharge compared to yesterday, aiming to maintain flood prevention capacity and ensure dam safety.

Tropical depression to enter the East Sea tomorrow

Tropical depression to enter the East Sea tomorrow

Over the past 24 hours, the tropical depression has mainly moved at a speed of 5-10 km/h; it is forecast to shift southward when entering the East Sea tomorrow due to interaction with cold air.

Eng English
China 中国人
  • News
  • World
  • Business
  • Entertainment
  • Sports
  • Law
  • Education
  • Health
  • Lifestyle
  • Travel
  • Science
  • Digital
  • Automobiles
FPT Tower, 10 Pham Van Bach Street, Dich Vong Ward,
Cau Giay District, Hanoi, Vietnam
Email: contacts@vnportal.net
Tel: 028 7300 9999 - Ext 8556
Advertise with us: 090 293 9644
Register
© Copyright 2025 vnnow.net. All rights reserved.
Terms of use Privacy policy Cookies