Four key roads in Thu Thiem accelerate towards completion

After years of delays, four key roads, spanning nearly 12 kilometers in Thu Thiem with a total investment exceeding VND 12 trillion, are seeing accelerated construction to ensure synchronous connectivity across the entire network.

The project for four main roads in the Thu Thiem New Urban Area, comprising Tran Bach Dang, To Huu, Nguyen Thien Thanh, and Bui Thien Ngo, commenced in April 2013 under a build-transfer (BT) contract. However, it faced years of delays due to site clearance issues.

Construction is now accelerating and is expected to be completed this year. Pictured are the Tran Bach Dang route, 3.4 km long (right), and the To Huu route, 3 km long, currently under construction and connecting at the Luong Dinh Cua - Tran Nao intersection.

Compared to 2018, construction on Tran Bach Dang street has now restarted in sections that were left unfinished and abandoned for many years. The route features a cross-section of 55 meters and six lanes.

The section of Tran Bach Dang near the Luong Dinh Cua intersection, which previously encountered site clearance problems for years, is now seeing accelerated construction to open the entire route to traffic soon.

Nearby, two overpasses that had been abandoned for nearly 10 years are now under construction again. According to the design, the four routes will include 10 bridges, along with a system of intersections, landscaping, and lighting.

Adjacent to Tran Bach Dang street is the construction site for To Huu street. This 3 km route still has nearly one kilometer unfinished after many years. To Huu street winds through the area, connecting with Nguyen Co Thach, Tran Bach Dang, and Mai Chi Tho streets. It also passes through the developing Thu Thiem administrative center.

Following To Huu street is the Bui Thien Ngo route (right corner), which is 2.5 km long, features a cross-section of over 11 meters for two lanes, and traverses the Sala urban area.

According to the master plan, this route encircles the ecological reserve of the Thu Thiem New Urban Area. The section passing through the Sala urban area was largely completed nearly 10 years ago, but currently sees little traffic.

Nguyen Thien Thanh street, 3 km long, features a cross-section of over 28 meters with two lanes, running along the Saigon River. This route is now largely complete.

The completed sections of the roads have been landscaped with trees and equipped with lighting systems, signage, and traffic markings.

The completion of these four main roads, along with other infrastructure projects, is expected to drive development in the Thu Thiem New Urban Area, fostering its emergence as a modern financial, commercial, and service hub for Ho Chi Minh City in the future.

Quynh Tran - Thanh Tung

By VnExpress: https://vnexpress.net/4-tuyen-duong-huyet-mach-o-thu-thiem-tang-toc-ve-dich-5076747.html
Tags: transportation infrastructure Ho Chi Minh City Thu Thiem New Urban Area

News in the same category

Thousands of tons of construction waste await removal in Hanoi

Thousands of tons of construction waste await removal in Hanoi

Hanoi is undertaking numerous transport and drainage projects, generating thousands of tons of construction waste daily, which puts significant pressure on waste management.

Hanoi proposes 8-lane expressway for ring road 5

Hanoi proposes 8-lane expressway for ring road 5

Hanoi recommends an 8-lane expressway for a section of Capital Region ring road 5, replacing the 6-lane option proposed by the Ministry of Construction.

Mass shrimp deaths: pond owner discovers eight carbide bags at bottom

Mass shrimp deaths: pond owner discovers eight carbide bags at bottom

After a single night, an entire stock of whiteleg shrimp in a 1,500 square meter pond in Phu Trach commune perished; upon draining the water, the owner found eight bags of calcium carbide at the bottom.

Male student dies after being sucked into water pump pipe

Male student dies after being sucked into water pump pipe

A 16-year-old male student died after being sucked into a pump pipe and getting trapped while swimming with friends at an irrigation pump station's intake pool in Bach Ngoc commune.

Red River banks: current state ahead of landscape boulevard plan

Red River banks: current state ahead of landscape boulevard plan

Beyond the Red River dike, the section through the capital's center is densely packed with houses stretching from the dike's base to the riverbank; the section through Me Linh commune is a renowned agricultural area.

Current status of over 7 km of Saigon River riverside road soon to be expanded to six lanes

Current status of over 7 km of Saigon River riverside road soon to be expanded to six lanes

Approximately 7,4 km of the riverside road through former Binh Duong is set for expansion with a total investment of 9,400 ty dong, creating a major transportation axis parallel to national highway 13 and aiming to alleviate regional traffic congestion.

Dong Nai to construct 43 km road linking Long Thanh airport

Dong Nai to construct 43 km road linking Long Thanh airport

Road 770B, 6-8 lanes wide and costing approximately 4,600 billion VND, will connect Long Thanh airport to industrial zones and key transport routes.

Relic procession marks Buddha's Birthday in Hanoi and Hue

Relic procession marks Buddha's Birthday in Hanoi and Hue

On the evening of 30/5, ceremonies to process Buddha's relics and statues for the Great Buddha's Birthday (Buddhist calendar 2570) took place across central streets of Hanoi and Hue, attracting numerous monks, nuns, and devotees.

Deputy prime minister: ensure people's interests when land is recovered for Red River scenic boulevard axis

Deputy prime minister: ensure people's interests when land is recovered for Red River scenic boulevard axis

Standing deputy prime minister Pham Gia Tuc requested Hanoi to ensure the legitimate rights and interests of people regarding compensation, support, and resettlement when land is recovered for the Red River scenic boulevard axis project.

Hanoi revokes 24 slow-moving projects

Hanoi revokes 24 slow-moving projects

Following a 1,5-month ultimatum to non-budgetary capital projects, the Hanoi People's Committee today announced the revocation of 24 slow-moving projects.

Eng English
China 中国人
  • News
  • World
  • Business
  • Entertainment
  • Sports
  • Law
  • Education
  • Health
  • Lifestyle
  • Travel
  • Science
  • Digital
  • Automobiles
FPT Tower, 10 Pham Van Bach Street, Dich Vong Ward,
Cau Giay District, Hanoi, Vietnam
Email: contacts@vnportal.net
Tel: 028 7300 9999 - Ext 8556
Advertise with us: 090 293 9644
Register
© Copyright 2026 vnnow.net. All rights reserved.
Terms of use Privacy policy Cookies