Long Thanh airport boosts workforce to meet year-end deadline

Contractors are increasing their workforce for the Long Thanh airport project as part of a "180-day sprint" campaign, aiming to complete the construction on schedule.

On 22/6, Airports Corporation of Vietnam (ACV) announced that nearly three weeks after launching the campaign, the construction site maintains an average of over 7,300 direct laborers, an increase of about 4,5% compared to 1/6.

According to ACV, contractors are mobilizing more personnel to accelerate progress on key packages such as the passenger terminal, internal airport traffic, and runway 2. Some units are also deploying hundreds of military officers and soldiers to support construction.

Workers construct the passenger terminal. Photo: Phuoc Tuan

To date, the total output value of sub-project three has reached over 65,600 billion dong, equivalent to nearly 76% of the signed contract value. Key construction and installation packages alone have achieved over 56,000 billion dong, equivalent to nearly 68% of the contract value, an increase of over 3% compared to early June.

"This indicates that the construction pace continues to accelerate following the launch of the peak campaign," an ACV representative stated.

For the internal airport traffic and technical infrastructure package, the investor is intensifying control across each area and item, requiring connection with related packages. The implementation value for package 4.8 currently stands at nearly 6,900 billion dong, equivalent to almost 62% of the contract value.

Entering the peak rainy season, ACV anticipates that weather conditions could impact outdoor construction activities, material and equipment transportation, and overall execution. The investor, along with relevant units, has developed response plans and adjusted schedules to suit actual conditions.

Inside the passenger terminal concourse. Photo: Phuoc Tuan

During a site inspection last week, leaders from the Ministry of Construction requested the investor, contractors, and related units to mobilize additional military forces to assist with cleanup, landscaping, and grass planting during the finalization stage.

Long Thanh Airport is being built on an area of about 5,000 hectares, with a total investment capital of nearly 16 billion USD. Phase one will have a capacity of 25 million passengers and 1,2 million tons of cargo annually. According to the plan, the airport will undergo trial operations in September before commencing commercial exploitation by the end of this year.

Phuoc Tuan

By VnExpress: https://vnexpress.net/san-bay-long-thanh-tang-nhan-luc-ve-dich-cuoi-nam-5088460.html
Tags: military Long Thanh airport labor

News in the same category

proposal to legalize special policies for reclaimed urban areas

proposal to legalize special policies for reclaimed urban areas

The government proposes a distinct mechanism for reclaimed urban areas with a scale of 100 trillion VND or more, aiming to create land funds and attract strategic investors, capital, technology, and high-quality human resources.

Relocating two helicopters from air force museum to Bien Hoa airbase

Relocating two helicopters from air force museum to Bien Hoa airbase

Mi8 and Mi24 helicopters, which participated in battles to protect the southwestern border, were relocated from the southern air force museum to Bien Hoa airbase for display.

Landslide causes national highway blockage in Quang Ngai

Landslide causes national highway blockage in Quang Ngai

Heavy rain caused hundreds of cubic meters of earth and rocks from an upslope embankment to spill onto National Highway 40B, along the bypass of Mang Roi Pass, leading to traffic congestion.

Avoid 'unreasonable disparity' in Ring Road 5 land compensation

Avoid 'unreasonable disparity' in Ring Road 5 land compensation

Land with similar conditions across administrative boundaries must receive equivalent compensation, preventing situations where those ceding land for Ring Road 5 receive different policies.

50 million VND reward offered for Trang Trinh temple bas-relief design

50 million VND reward offered for Trang Trinh temple bas-relief design

Hai Phong City has launched a bas-relief design competition for the special national relic Nguyen Binh Khiem Temple, with the first prize set at 50 million VND.

National Assembly to consider abolishing Supreme People's Procuracy investigation agency

National Assembly to consider abolishing Supreme People's Procuracy investigation agency

The National Assembly will review a proposal to disband the investigation agency of the Supreme People's Procuracy, transferring its authority to investigation bodies within the police and military.

Tropical depression heading into the Gulf of Tonkin, potential to strengthen

Tropical depression heading into the Gulf of Tonkin, potential to strengthen

A tropical depression east of Hainan Island, China, is forecast to enter the Gulf of Tonkin, potentially strengthening to level 7, gusting level 9, causing rough seas from 21/8.

Vietnamese soldiers and African students share traditional bamboo dance

Vietnamese soldiers and African students share traditional bamboo dance

Vietnamese and Chinese blue beret forces organized cultural exchange events, inviting children in Abyei to participate in traditional games from both nations.

Fire engulfs sewing thread and PE film factory in Hanoi

Fire engulfs sewing thread and PE film factory in Hanoi

A 1,000 square meter factory, part of the Quat Dong Industrial Cluster, was engulfed in flames on the evening of 19/8.

Teacher couple loses everything as 10 hectares of rice submerged in flood

Teacher couple loses everything as 10 hectares of rice submerged in flood

During his summer break, teacher Do Minh Hieu borrowed and gathered over 300 million VND to rent land for rice cultivation. Just before harvest, rapid floods completely submerged his entire crop.

Eng English
China 中国人
  • News
  • World
  • Business
  • Entertainment
  • Sports
  • Law
  • Education
  • Health
  • Lifestyle
  • Travel
  • Science
  • Digital
  • Automobiles
FPT Tower, 10 Pham Van Bach Street, Dich Vong Ward,
Cau Giay District, Hanoi, Vietnam
Email: contacts@vnportal.net
Tel: 028 7300 9999 - Ext 8556
Advertise with us: 090 293 9644
Register
© Copyright 2026 vnnow.net. All rights reserved.
Terms of use Privacy policy Cookies